PROJECT NAME
DEVELOPMENT OF YAK AT HIGH ALTITUDE AREA OF PAKISTAN (GB)
PROJECT DIRECTOR NAME
Contact No:
Email:
LOCATION
Gilgit- Baltistan ( GB)
SPONSORING AGENCY
Ministry of National Food Security and Research
EXECUTING AGENCY
Livestock and Dairy Development Board(LDDB)
ORIGINAL COST
Rs. 59.500
SCOPE
- Increase production 15-20 % of Yak through support to yak farmers for proper feeding, breeding, disease control, shelter & management.
- Development of yak promotion clusters in potential valleys.
- Development of feedlot fattening of market-able animals with the active participation of farmers and entrepreneurs.
- Assistance in the development of hygienic butcheries in the private sector of Gilgit-Baltistan.
- Capacity building of Yak entrepreneurs for value addition, meat production, processing and quality.

- Artificial Insemination of Semen has been done 132 Local cows Females Yaks
- Number of 04 Butcheries established in District Gilgit, Ghizer and Skardu
- No of 550 Yak/ zho animals dewormed.
- No of 400 Yak/ zho animals registered
- Self-employment generation
- Improve Livelihood of Farmers
- Improve capacity building of Farmes
- Self-sustaining of Yak entrepreneurs
PROJECT DETAILS
Date of approval with Forum | ||
Original date | Revised Date, if any | All subsequent Revisions (if any) |
16-04-2018 | N/A | N/A |
Financial Arrangement | Federal | |
Donor (if any)along with a share of foreign aid in the cost | NIL | |
Actual Date of Commencement | July 2018 | |
Completion Date (as per PC-I) | June 2021 | |
Likely Completion Date | June 2021 | |
Reason of Time and Cost Overrun | N/A | |
Specific decision/ recommendation made during previous quarterly reviews of PSDP 2019-20 | NIL | |
PMES system updated on (please specify date) | PMES system Updated up to 31stDecember 2020 |
Financial progress | ||
a) Expenditure up to June 2020 | 27.880 | |
b) %age Financial progress to-Date | 34% (As per release for year 2020-21 ) | |
Physical completion (in %age terms) | 35% | |
Allocation 2020-21 | Rupee | Foreign loan(if any) |
19.0 Million | Nil | |
Releases 2020-21 | Rupee | Foreign Loan(if any) |
9.500 Million | Nil | |
Expenditure/Utilization 2020-21 (July-Sept 2020) | Rupee | Foreign loan(if any) |
3.265 Million | Nil | |
Bottlenecks/Issues impeding progress on the project (if any) | NIL | |
Latest implementation status of the decision/recommendation | NIL |