PROJECT NAME

NATIONAL PROGRAM FOR THE IMPROVEMENT OF WATERCOURSES IN PAKISTAN: PHASE-II

PROJECT DIRECTOR NAME

Contact No:

Email:

LOCATION

Punjab
Khyber Pakhtunkhwa (KP)
Balochistan
Gilgit Baltistan (GB)
Azad Jammu & Kashmir (AJ&K)
Islamabad Capital Terrority (ICT)

SPONSORING AGENCY

Government of Pakistan through Ministry of National Food Security & Research (M/o NFS&R), Islamabad and respective Provincial Governments

EXECUTING AGENCY

M/o NFS&R through Federal Project Management Unit (FPMU). All Provincial Departments of Agriculture (Provincial Directorates of OFWM) and respective departments of AJ&K, GB and ICT. District Governments. Farmers Organizations/ Water Users Associations (WUAs).

ORIGINAL COST

154,542.355

SCOPE

Improvement of 47,278 watercourses up to 50% of total length, construction of 14,932 water storage tanks and provision of 11,610 Laser land levelers.
Objectives:

  • Social mobilization through capacity building of WUAs/ FOs
  • Minimization of conveyance and field application losses
  • Reduction in water logging and salinity
  • Equity in water distribution
  • Reduction in water disputes/thefts/litigation
  • Motivation/participation of farmers
  • Poverty reduction through employment generation
  • Increase in crops yield/sufficiency in food
Executing Agency Targets (PC-I) Achievements (Up-to December 2020)
Watercourses Water Storage Tanks Laser Land Levelers Watercourses Water Storage Tanks Laser Land Levelers
Punjab 10000 3000 9500 1229 201 1486
KP 13000 5000 600 1575 429 0
Balochistan 20389 5507 1500 1878 360 15
GB 2500 825 5 210 131 0
AJK 1165 600 5 119 76 0
ICT 224 0
Water saving per Watercourse per annum (AF):

Watercourse to be improved (Nos):

Estimated water to be saved per annum (MAF):

Estimated Economic Value per MAF under present productivity conditions (Million US$):

Total economic benefit due to saved water (Billion US$):

Billion Pak Rupees (1US$ = Rs.156)

123

47,278

5.82

400

2.33

363.5

Direct appointments of about 350 persons all over the country and employment opportunities of about 124,420 persons counting to 44.79 million man-days will become available for skilled and unskilled labor during execution of project activities including watercourse improvement, manufacturing of PCPS etc.

PROJECT DETAILS

Date of approval with Forum
Original date Revised Date, if any All subsequent Revisions if any
29th August 2019 (ECNEC) N/A N/A
Financial Arrangement GoP Share Rs. 47,175.504 million
Prov. Govt. Share Rs. 59,084.565million
Farmers’ Share Rs. 48,282.287million
Donor (if any)along with a share of foreign aid in the cost N/A
Actual Date of Commencement 1st October, 2019 (Admin Approval)
Completion Date (as per PC-I) 30th June 2024 (Extendable)
Likely Completion Date 30th June 2024
Reason of Time and Cost Overrun N/A
Specific decision/ recommendation made during previous quarterly reviews of PSDP 2019-20
  • Monthly progress will be regularly updated in PMES of the M/o PD&SI by 25th of each month.
  • Baseline of each project (percentage progress physical and financial) will be indicated by 1st July, 2020 and quarterly targets will be indicated on PMES by each PD by 15th October 2020.
PMES system updated on (please specify date) 19th January 2021
Financial progress
a) Expenditure up to June 2020 3,944.336
b) %age Financial progress to-Date 10.8%
Physical completion (in %age terms) 10.4%
Allocation 2020-21 Rupee Foreign loan(if any)
Rs. 5,250.00 million Nil
Releases 2020-21 Rupee Foreign Loan(if any)
Rs. 1,840.00 million Nil
Expenditure/Utilization 2020-21 (July-Sept 2020) Rupee Foreign loan(if any)
Rs. 1,082.113 million Nil
Bottlenecks/Issues impeding progress on the project (if any)
  • Late receipt of reconciliation statement from the Executing Agencies.
  • In recent Scenario of restrictions by the State Bank of Pakistan, difficulty in opening of WUA’s accounts which is hampering field work.
  • Delay in recruitment of project staff due to COVID-19 and completion of procedural formalities
  • Delay in procurements for FPMU due to COVID-19, hiring of office building and completion of procedural formalities.
Latest implementation status of the decision/recommendation Complied with