PROJECT NAME

PILOT SHRIMP FARMING CLUSTER DEVELOPMENT PROJECT

PROJECT DIRECTOR NAME

Contact No:

Email:

LOCATION

Punjab, Sindh & Balochistan

SPONSORING AGENCY

Ministry of National Food Security and Research
Forest, Wildlife & Fisheries Department, Govt. of Punjab
Livestock and Fisheries Department, Govt. of Sindh.

EXECUTING AGENCY

Fisheries Development Board
Department of Fisheries Punjab
Department of Fisheries Sindh

ORIGINAL COST

6381.86 Million

SCOPE

  • Promotion of shrimp aquaculture in inland areas.
  • Development of shrimp value chain, support services and legal framework.
  • Livelihood and job creation for rural people.
  • Export earnings from inland aquaculture.

Federal Component

  • Staff hired for PMU.
  • The hiring of Project Manager Completed.
  • Necessary procurement for PMU completed
  • Land identified for establishment of 01 Model Shrimp farm file in process for section 4 with DC Jhelum and revenue department.
  • The site identified for Hatchery and negotiations with Pakistan Navy for land provision is under process.

Punjab Component

  • PIU established, PD appointed
  • The site selected for the Saline water Aquaculture Research Centre at Muzaffargarh and civil work awarded.
  • Civil work awarded for up-gradation of training centers at Bahawalpur and Rawalpindi.
  • Conducted experiment on Artemia culture.
  • Construction and renovation of Training hostels are in process.

Sindh Component

  • Sindh is still not part of the project.

The Project will help to improve the activities related to fisheries and will provide opportunities to different parts of society to improve its prosperity. The extra activities generated by the project will generate employment for the unemployed part of society. This will improve the social interaction of society and ultimately will enhance peace and remove the negative attitudes in society. Direct employment will be generated as the project will be in operation. Moreover, indirect employment will be generated in the other relevant sectors of the economy through this project.

PROJECT DETAILS

Date of approval with Forum
Original date Revised Date, if any All subsequent Revisions if any
29-8-2019 N/A N/A
Financial Arrangement PSDP/ADP
Donor (if any)along with a share of foreign aid in the cost N/A
Actual Date of Commencement 23-12-2019
Completion Date (as per PC-I) 30-06-2024
Likely Completion Date 30-06-2024
Reason of Time and Cost Overrun N/A
Specific decision/ recommendation made during previous quarterly reviews of PSDP 2019-20 NIL
PMES system updated on (please specify date) 12/12/2020
Financial progress
a) Expenditure up to June 2020 PSDP- 7.11
ADP- 14.268
b) %age Financial progress to-Date PSDP +ADP = 32.00 %
Physical completion (in %age terms) 10%
Allocation 2020-21 Rupee Foreign loan(if any)
PSDP- 200 Million
ADP- 45.472 Million
Nil
Releases 2020-21 Rupee Foreign Loan(if any)
PSDP- 40 Million
ADP- 45.472 Million
Nil
Expenditure/Utilization 2020-21 (July-Sept 2020) Rupee Foreign loan(if any)
Federal: 4.562
Punjab: 22.774
Nil
Bottlenecks/Issues impeding progress on the project (if any) Federal Component;

  • Progress slow due to COVID-19.
  • Land Acquisition is taking time and all activities are pending due to land acquisition issues.
  • NOC from Navy is pending.

Punjab component;

  • Funds not release as per PC-1 provision which caused delay to project activities implication on project.
Latest implementation status of the decision/recommendation NIL