PROJECT NAME

STRENGTHENING OF AGRICULTURE AND LIVESTOCK RESEARCH SYSTEM OF ARID ZONE RESEARCH INSTITUTE, UMERKOT-SINDH

PROJECT DIRECTOR NAME

Contact No:

Email:

LOCATION

PARC-Arid Zone Research institute, Umerkot

SPONSORING AGENCY

M/o NFS&R through PSDP

EXECUTING AGENCY

Pakistan Agricultural Research Council, Islamabad

ORIGINAL COST

Rs. 509.26 million

REVISED COST

Rs. 528.592million

SCOPE

  • To strengthen and upgrade the crops and livestock research infrastructure and technical manpower
  • To establish a new Livestock field research program to address the livestock production related issues
  • To impart short and long-term capacity building programs in order to address the issues of crop and livestock farmers of Thar.
  • To strengthen the linkages with provincial and international research organizations
  • 32 acres orchard has been planted on the drip irrigation system and 8 acres (Grafted ber) will be planted on saline underground water with 4500 ppm irrigated through drip irrigation system using solar energy for pumping.
  • Germplasm of the 38 exotic & indigenous varieties of Date palm has been collected from different sources and planted at the institute farm.
  • 11 different varieties of Guava have been collected and planted at the institute farm.
  • The construction work of the office building and laboratories is in progress and more than 45% work completed. Civil work of Rs. 58.5 million is also in progress.
  • The staff members recruited and the remaining 09 staff members will be recruited shortly as NoC received from M/o NFS&R.
  • MoU has been signed between Thar Coal Authority and Thardeep as collaborative activities can be made in the Desert area of Thar.
  • 2 seminars for knowledge sharing and training programs have been arranged.
  • Tree plantation has been done at institute farm where Deputy Commissioner Umerkot, Brigadier of ChhorCant and other socialists planted the trees.
  • A visit of the Chairman, Member NRD, Member PSD PARC with DG SARC, has been arranged to evaluate the progress of the project.
  • The Project Technical Committee meeting was held on zoom, chaired by the Member NRD, PARC.
  • Supply order of Research Equipment, Office and Computer Equipment issued worth Rs. 7.730 million.

PROJECT DETAILS

Date of approval with Forum
Original date Revised Date, if any All subsequent Revisions if any
03.05.2017 N/A N/A
Financial Arrangement Federal
Donor (if any)along with a share of foreign aid in the cost N/A
Actual Date of Commencement 30-07-2017
Completion Date (as per PC-I) 30-06-2022
Likely Completion Date 30-06-2022
Reason of Time and Cost Overrun N/A
Specific decision/ recommendation made during previous quarterly reviews of PSDP 2019-20 NIL
PMES system updated on (please specify date) 12/31/2020
Financial progress
a) Expenditure up to June 2020 167.854 million
b) %age Financial progress to-Date 42.78%
Physical completion (in %age terms) 35%
Allocation 2020-21 Rupee Foreign loan(if any)
116.601 million Nil
Releases 2020-21 Rupee Foreign Loan(if any)
58.300 million Nil
Expenditure/Utilization 2020-21 (July-Sept 2020) Rupee Foreign loan(if any)
19.479 Nil
Bottlenecks/Issues impeding progress on the project (if any) N/A
Latest implementation status of the decision/recommendation NIL